1. Home
  2. Offshore wind energy
  3. Permit for IJmuiden Ver Wind Farm Site Gamma-B

Permit for IJmuiden Ver Wind Farm Site Gamma-B

The content of this page has been checked on 25 August 2026

Are you a wind farm developer or energy company looking to invest in the construction and operation of a offshore wind farm with a capacity of around 1 gigawatt (GW)? If so, apply for a permit with subsidy for the Gamma-B site in the IJmuiden Ver Wind Farm Zone. On this page, you can read about the steps to submit an application.

Budget

Start date:
Thursday 26 November 2026
00:00 (CEST)
End date:
Thursday 10 December 2026
17:00 (CEST)
Total budget:
€4,698,000,000

Who is this for?

Wind farm developers and energy companies can participate in this permit round. This subsidy tender is for businesses committed to generating sustainable energy and contributing to the tranistion from fossil fuels to renewable energy (energy transition). We are organising a subsidy tender for this permit. The best application will receive the permit and subsidy.

By building and operating a offshore wind farm on the Gamma-B site, you are contributing to the further development of the offshore wind energy sector in The Netherlands. This strengthens the energy independence and resilience of the Dutch energy system.

IJmuiden Ver Wind Farm Site Gamma-B

Location of the IJmuiden Ver Gamma-B site

Which areas are involved?

IJmuiden Ver Site Gamma-B is located in the North Sea, approximately 61 km off the west coast of the Netherlands. The site covers an area of 95 km2 and provides space for a 1 GW offshore wind farm.

Site Gamma-B is part of the IJVWFZ. This zone consists of 4 sites (Alpha, Beta, Gamma-A, and Gamma-B), with a total area of approximately 609 km2 (including maintenance and safety zones). Together, these 4 sites can support around 6 GW of installed offshore wind energy capacity.

Permits for the IJV Alpha and Beta sites were issued in 2024. More information about these sites can be found at Permits for wind farms at IJmuiden Ver Alpha and Beta. In January 2026 we announced the permit round for the IJmuiden Ver Gamma-A site.

How does electricity get from sea to land?

Transmission system operator TenneT is installing the offshore grid that will connect the wind farms to the onshore high-voltage grid. This is how the wind energy generated is fed into our electricity grid. The wind farm will be connected to a TenneT substation platform for this purpose. The platforms have a 2 GW Direct Current (DC) connection to an onshore substation. This means that 2 wind farms, each with a capacity of 1 GW, will be connected to a single platform. The DC connection ensures a constant voltage on the electricity grid.

The IJV Gamma-A and IJV Gamma-B sites (both 1 GW capacity) will connect to a single offshore energy platform. This ensures the best possible use of the offshore grid. Connecting both sites to a single platform also requires less work and time.

For more information about the offshore grid, see the Offshore Wind Energy Development Framework in Landfall of offshore wind energy: from sea to land. The Development Framework covers topics such as the design, construction, and lifespan of the offshore grid.

The development framework was recently updated following the release of the final regulations for IJVWFZ Gamma-A and IJVWFZ Gamma-B. You can read the full updated document (May 2026) and the corresponding Letter to Parliament in the Official Announcements below.

How much subsidy can you receive?

You can choose whether to apply for a subsidy or to submit a subsidy-free bid in an auction.

Both procedures run simultaneously. For the Gamma-B site subsidy permit, you can apply for a maximum subsidy of € 4.698 billion. Or you can submit a subsidy-free bid in an auction. The maximum tender amount for IJV Gamma-B is € 0.116 per kilowatt-hour (kWh).

We determined this maximum tender amount based on a potential feed-in tariff from the Netherlands Authority for Consumers and Markets (ACM). If this tariff is introduced, electricity producers will have to contribute to the cost of the electricity grid. As a wind farm developer, this could create uncertainty and increase your costs. With this subsidy amount, we ensure that you can still make a profit with your wind farm.

Conditions

You must meet a number of general conditions and pre-qualification criteria. These are outlined in the final regulations (attached below). The conditions apply to all applications (with or without subsidy). We will rank your application if it meets the pre-qualification criteria and general terms.

  • We process auction bids first, followed by subsidy applications.
  • In the auction, the application with the highest bid ranks first.
  • For subsidy applications, the lowest subsidy request ranks first. 
  • The highest-ranked application receives the permit—and, in the case of the subsidy procedure, the subsidy.

Preparing your application

We will post important documents for your application on this page. This allows you to start preparing your application well before the application period opens. The following documents are already available. An explanation is provided with each document. We will continue to supplement these documents.

Form providing security information

Since 1 January 2026, a mandatory safety assessment is part of the Offshore Wind Energy Act. This assessment is conducted by the Investment Assessment Agency (BTI). The BTI checks whether your company can safely and reliably build and operate a wind farm at sea.

Fill in the form and provide information about your company, such as:

  • financial details
  • technical experience
  • safety measures

Send the form to the BTI, before the tender closes.

Only available in Dutch.

Operating calculation

In the operating calculation, you report all the costs and revenues of the wind farm. The model then automatically calculates the financial result of your project over its entire term. This prevents your bid from being unrealistic. Furthermore, under the Offshore Wind Energy Act, we may only issue a permit if there is sufficient confidence that the wind farm is economically viable.

The operating calculation is a draft. Feel free to send us any questions or feedback via e-mail to woz@rvo.nl.

Only available in Dutch.

Wind Farm Site Decision

Use the Wind Farm Site Decision (WFSD) to prepare your application. It contains site boundaries and the conditions you must adhere to when building and operating the wind farm. These conditions include, among other things, nature conservation. This WFSD for IJV Site Gamma-B (in Dutch) became irrevocable on 28 June 2025.

For your reference, we have provided an unofficial translation of the regulations (attached below). This is an updated version. The previous version contained incorrect coordinates.

Amendments to Wind Farm Site Decisions

In addition to the WFSD, you will also need the Amendments to Wind Farm Site Decisions (WFSDs) for your application in upcoming tenders. This is because the amended WFSDs contain important adjustments that were not included in the previous version of the WFSD. Without this information, your application will be incomplete. Some amendments also apply retroactively to projects already operating or permitted and under construction.

Wind farm temporarily shut down during bird migration

With the January 2026 WFSD amendments (in Dutch), we are adjusting the rules for wind farms in the Borssele, Hollandse Kust, IJmuiden Ver, and Nederwiek Wind Farm Zones. We aim to prevent bird strikes with this measure.

We are doing this by:

  • temporarily shutting down turbines during mass bird migration;
  • using a prediction model to determine when this is necessary;
  • limiting the downtime of turbines to a maximum of 60 hours per year.

Read more about this WFSD amendment (in Dutch).

Cybersecurity in wind farms

With the February 2026 amendments (in Dutch), we are amending the WFSDs for IJmuiden Ver Gamma-A and -B, and Nederwiek I-A. It is now mandatory for the management of wind farms to take place within the European Economic Area (EEA). This ensures compliance with the new EU rules on cybersecurity and data security.

Read more about this WFSD amendment (in Dutch).

Permit regulations

The permit holder must adhere to a number of regulations when carrying out the project. The draft permit regulations contain the regulations that will, in any case, be included with the final permit. We determine the final regulations with the permit. These may depend on what you state or promise in your bid.
Only available in Dutch.

Site characterisation studies

Together with our partners, we conduct site studies in the IJVWFZ. The data and reports from the site studies are published on offshorewind.rvo.nl (English). With the data from these site studies, you can plan and optimise the design of the offshore wind farm.

Memo Boundaries & Coordinates IJV Site Gamma-B

The Memo Boundaries & Coordinates for IJmuiden Ver Site Gamma-B is available upon request. The information in the Memo is confidential. To request a copy of the Memo, you can send an email to woz@rvo.nl.  

We will then assess your application. If your request is approved, we’ll ask you to sign a Non-Disclosure Agreement (NDA) before receiving the Memo.

The Memo includes:

  • a Word file with maps, figures and tables
  • an Excel file with the corresponding coordinates

You can use the coordinates and boundaries in this memo to design your future offshore wind farm.

Step-by-step plan for your application

Step 1: gather the required attachments

When submitting your application, there are attachments that you must submit as mandatory. You will soon find out on this page which supporting documents are required and what information they must contain.

Step 2: create your application

You can submit your application during the application period. Follow these steps:

  • Click on the button: 'Submit your application now' at the top of this page. You will then enter our digital application environment.
  • Log in using eHerkenning or DigiD.
    • For your application with eHerkenning (online authentication), you need at least level 3 with authorisation for RVO services at level eH3.
    • If you do not have eHerkenning yet, apply for it in time. Please note that processing may take several working days.
    • It is not possible to submit an application with a chain authorisation. Read more about the different ways to log in.
  • First time logging in? You will be directed to a profile page. Fill in all the mandatory fields and save them. You will then be logged out and must log in again.
  • Via the tab 'Nieuwe aanvraag' (new application), select the form for this application round. The exact name of the form will be available on this page at a later date.
  • Complete all the required details for your application in the form.
  • Review your input using the button 'Controleer' (check) before moving to the next tab. If any information is missing or incorrect, you will receive a notification.
  • In the last tab of the application form, you will upload the attachments. Mandatory attachments are marked with an asterisk (*).
  • Double-check your application for errors before submitting it. If you receive error messages, go to the relevant tab and correct your input.

Please note the following:

  • Your application form will be automatically saved when you move to the next tab. You can also save your data manually in between. You can log out after saving, and log back in later to continue from where you left off.
  • Scan all your attachments first and upload them into the digital application environment. If a file exceeds the 40 MB limit per attachment, submit the attachment in multiple parts along with your application.

Step 3: submit your application

  • To submit your form, click on the button 'Naar verzenden' (proceed to submission) under the tab 'Controleren' (check) in the digital application environment. All the questions and answers will then be displayed on the screen. Carefully check your application again and ensure that you have attached all the necessary permits and attachments.
  • Tick the box 'Verklaring en ondertekening' (declaration and signature). Submit your application definitively by clicking the button 'Ondertekenen en verzenden' (sign and submit).

Please note the following:

  • Immediately after submission, you will receive a confirmation of receipt with a project number at the email address you provided in your profile. You will use this number for any correspondence regarding your application.
  • You can find your application and the confirmation of receipt under 'Mijn aanvragen' (my applications) in the digital application environment, as long as you are still authorised.

After your application

After the application period closes, we expect:

  • To grant the permit in the first quarter of 2027.
  • For IJmuiden Ver Gamma-B to become operational in 2032.

Questions and answers on the permit

Below you will find answers to questions about the application stage (in Dutch). We update this document regularly. We will send you a notification as soon as a new version is available.

Want to know more?

Questions about offshore wind energy?

If you have any questions about offshore wind energy, feel free to email us at woz@rvo.nl.

Stay updated

Tip: want to stay informed about updates to this page? Click the 'Stay informed via email' button at the top of this page. You’ll receive an email whenever the information on this page changes.